Valley View Avenue Interchange

Galleries


Valley View Avenue Interchange


In mid-November  of 2016 Caltrans began construction on the Valley View Avenue Interchange Project, which will add a High Occupancy Vehicle and mixed-flow lane in each direction along approximately one and a half miles of I-5 at Valley View Avenue, from Artesia Boulevard undercrossing to North Fork Coyote Creek. The project extends through the cities of Buena Park, La Mirada, Cerritos, and Santa Fe Springs.

Three bridges will be reconstructed: the Valley View Avenue Bridge at I-5, the North Firestone Boulevard Bridge over Coyote Creek, and the I-5 freeway bridge at Coyote Creek. Lanes will be kept open on the Valley View Avenue Bridge during construction. There will also be improvements to the interchange at Valley View Avenue and adjacent frontage roads. The new bridge will include a railroad overpass.

Construction on this project is 43% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Revised to *late 2019.
Completion of second half of Valley View Ave. Bridge: Revised to *late 2021.
Completion of entire I-5 Valley View Ave. Interchange project: Revised to *late 2021.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

There are currently three sections of the first half of the Valley View Ave. Bridge under construction:

  1. One section crosses over I-5 in Santa Fe Springs. Final concrete was poured on the deck on the night of November 8. Photos below:
  2. A second section crosses over Arbor Pl. in Cerritos. The final layer of concrete has been poured on this section and most of the falsework has been removed from the sides. Photos below:
  3. A third, middle section will cross over the railroad tracks. Crews have completed pouring concrete over the “soffit” (underside) of the deck and within the “stem walls”. They are removing the forms and placing them horizontally as a base for another layer of rebar. Photos below from June 5 and June 11:
  4. The contractor has completed constructing the soffit and the stem walls along the edge of the deck of the ramp that will connect Firestone Blvd. to the Valley View Ave. Bridge. Workers completed laying rebar and building vertical rebar stem walls where the ramp meets the bridge. Now they are securing forms to the the rebar stem walls in preparation for a concrete pour. Photos below from May 14, May 28, and June 5, and June 11:
  5. Workers are constructing “falsework” (temporary frame support) for the Valley View Ave. off ramp from southbound I-5 crossing over the support columns and connecting to the bridge. Photos below from June 11:

 

  1. Primary construction of two bridges side-by-side over Coyote Creek east of I-5 near Trojan Way in La Mirada is complete. One bridge will carry new lanes of Firestone Blvd. and one will carry the new lanes of I-5. The contractor is constructing new lanes of northbound I-5 between Knott Ave. and Trojan Way. Photos below:
  2. Firestone Blvd. is restricted to one lane in each direction between Valley View Ave. and the Firestone Blvd. off ramp from northbound I-5 in La Mirada. Trucks over 25′ in length and /or over 2500 lbs. may NOT:
    1. Turn left onto Firestone Blvd, from the off ramp. (Right turn only permitted).
    2. Turn left on Firestone Blvd. from Valley View Ave.Detour map below:

    N. Firestone Blvd. is closed between Knott Ave. and Trojan Way to allow widening of northbound I-5, reconstruction of a new Firestone Blvd, to the east, and the reconstruction of Coyote Creek Bridge. Detour map below:

    Project Map