Valley View Ave. Interchange Project – Week of September 14- September 21, 2018

Construction on this project is 32% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Approximately March of 2019.
Completion of second half of Valley View Ave. Bridge: Approximately December of 2020.
Completion of entire I-5 Valley View Ave. Interchange project: Approximately early 2021.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

 

The portion of the Valley View Ave. Bridge over I-5 now connects to the pier wall west of S. Firestone Blvd in Santa Fe Springs. Installation of the rebar frame support walls and concrete molds is complete. 1700 cubic yards of concrete was poured onto the deck of the bridge the night of Monday, Sep. 17. Photos below are from September 4 & September 11. (Tap / click on photos for slide show and details):

 

Workers installed  a horizontal grid of rebar over the lumber deck surface of the Valley View Ave. Bridge over Arbor Place in Cerritos. The contractor then poured concrete over the rebar on Tuesday, September 11. This is the final layer of concrete for this section of the bridge and this is the concrete surface over which vehicles will drive. The concrete is covered with tarps to allow proper curing .Photos below show progress between August 21 and September 11:

 

Workers completed constructing the rebar frame for the pier walls that will support the new bridge over Coyote Creek. east of I-5 near Trojan Way in La Mirada. This past week they  started building the lumber molds over the rebar. The next step will be to encase the rebar in concrete. Photos below show progress from September 4 to September 11:

 

Caltrans recycles! Our contractor crushes concrete salvaged from the demolished structures of our project and crushes it into aggregate used for the base layer of freeway pavement and for back-filling retaining walls and structure walls.  Photos below from September 4:

 

The footing and rebar frame for a future retaining wall east of I-5  at the Valley View Ave. Bridge (September 4, below):

 

Valley View Ave. will be elevated to meet with the new Valley View Ave. Bridge. In turn, N. Firestone Blvd. will be elevated to meet Valley View Ave. In preparation for these modifications, N. Firestone Blvd. is now reduced to one lane in each direction between Gateway Dr. and Valley View Ave. Trucks over 2,500 lbs. and /or 25′ long are not permitted. Click “play” arrow below:

Restrictions:
Trucks 2500 lbs. or more and / or at least 25’ long will not be permitted to:
• Drive on N. Firestone Blvd. between Valley View Ave. and Gateway Dr.
• Turn left or right onto N. Firestone Blvd. from Valley View Ave.
• Turn left from the northbound I-5 Valley View Ave. exit ramp at Gateway Dr.
to access Valley View. They must turn right onto N. Firestone Blvd.

Access to all local businesses will remain open.

Through the remainder of this project, there will be recurring closures of:
N. Firestone Blvd. between Valley View Ave. and Gateway Dr.
Valley View Ave. between Alondra Blvd. and Park Place.
Access to businesses within those closure parameters will ALWAYS be permitted. Secure the attention of workers on scene to allow access, if necessary.

N. Firestone Boulevard is CLOSED between Knott Avenue and Trojan Way in La Mirada until at least April of 2019 to prepare for the widening of I-5 and to allow demolition and reconstruction of the bridge over Coyote Creek. N. Firestone Boulevard will be rebuilt to the east. Closure and detour map below:

 


DISCLAIMER
: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.

Print Friendly, PDF & Email