VALLEY VIEW AVENUE INTERCHANGE PROJECT – Nov 3, 2017

There will be multiple overnight full freeway closures Friday, Nov. 3 through Monday, Nov. 6. Crews will be shifting

Beginning Friday, Nov. 3 – Paving

  • Southbound I-5 two right lanes closed from Alondra Boulevard to Artesia Avenue (12:01 a.m. to 4 a.m.) One lane will remain open.
  • Full freeway closure of northbound I-5 between Artesia Boulevard and Valley View Avenue (1 a.m. to 5 a.m.)
  • Valley View Avenue on-ramp to northbound I-5 closed for 55 hours (7 p.m. Friday, Nov. 3 through   6 a.m. Monday, Nov. 6)
  • Valley View off-ramp from northbound I-5 closed (9 p.m. to 10 a.m.)
  • Northbound I-5 two right lanes might close (11 p.m. to 5 a.m.). One lane will remain open.

Beginning Saturday, Nov. 4 – Striping & K-Rail Placement

  • Southbound I-5 two right lanes closed from Alondra Boulevard to Artesia Avenue (12:01 a.m. to 4 a.m.) One lane will remain open.
  • Valley View off-ramp from northbound I-5 closed (7 p.m. to 11 a.m.)

Beginning Sunday, Nov. 5 – Striping & K-rail

  • Full freeway closure of northbound I-5 between Artesia Boulevard and Valley View Avenue (1 a.m. to 8 a.m.)

Monday, Nov. 6 – Striping & K-rail

  • Full freeway closure of southbound I-5 between Carmenita Road. and Artesia Boulevard (12:01 a.m. to 5 a.m.)

The closure area is shown in red on the map below; detour route shown in green.

 

 

Shoring activities are ongoing on the south side of Valley View Avenue. This work will be conducted weekdays during the daytime between 7 a.m. and 3:30 p.m.

DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.