Valley View Ave. Interchange Project – June 14- June 21, 2019

Construction on this project is 43% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Revised to *late 2019.
Completion of second half of Valley View Ave. Bridge: Revised to *late 2021.
Firestone Blvd. reverts to two lanes in each direction at Valley View Ave.: End of 2021. 
I-5 Valley View Ave. Interchange projected date of completion: Revised to *End of 2021.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Scheduled to be closed from 9 p.m. to 6 a.m. each night from the night of Monday, June 17 through the night of Thursday, June 20 for sewer line work:
Southbound Valley View Ave. from Alondra Blvd. to Artesia Blvd. 
Northbound Valley View Ave. from Arbor Place to Alondra Blvd. 
N. Firestone Blvd. from Gateway Dr. to Valley View Ave.  

Scheduled to be closed from 9 p.m. Tuesday, June 18 to 6 a.m. Wednesday, June 19 for a concrete pour:
S. Firestone Blvd. from Marquardt Ave. to the Valley View Ave. Bridge. Business access will be permitted. 

These closures are scheduled for separate nights and will re-open each morning. All closures subject to change.  Watch for updates at twitter.com/My5LA. 

Click to view videos of work in progress on I-5 Valley View Av. Bridge from June 11 below:

View of the future Valley View off ramp from southbound I-5. Panning south towards the new Valley View Ave. Bridge. This is the falsework, or temporary frame structure support, over which the ramp will be constructed. View from below, from June 11:

View from above, June 11:

View of Valley View Ave. Bridge panning northeast toward I-5. Workers are removing forms from rebar stem walls now encased in concrete and placing them horizontally. June 11, below:

Future Firestone Blvd. ramp panning towards bridge. Workers are securing molds to rebar stem walls June 11, below:

Concrete has been poured over the “soffit” (deck underside) and inside the rebar frames of the stem walls on the valley View Ave. Bridge. Workers continue to remove the forms from the stem walls. They are also building frames to lay the forms horizontally to provide support to place another layer of rebar. Photos below from June 5 and June 11:

On the future Firestone Blvd. ramp to the Valley View Ave. Bridge, workers finished installing rebar on the “soffit” (underside of the deck) and the stem walls. Now they are securing forms to the stem walls in preparation for a concrete pour. Photos below from May 14, May 28, June 5, and June 11:

Workers are now building the “falsework” (temporary frame support structure) for the future Valley View Ave. off ramp from soutbound I-5 that will connect the ramp an support columns to the deck of the bridge. Photos below from June 11:

In La Mirada, the contractor is constructing new lanes of northbound I-5 between Knott Ave. and Trojan Way approaching the new Coyote Creek Bridge. Photos below from June 5: