Valley View Ave. Interchange Project – July 31, 2020 – August 7, 2020

Construction on this project is 66% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Opened to traffic Monday, October 7, 2019. A second southbound lane will open in *the summer of 2020. 
Completion of second half of Valley View Ave. Bridge: Revised to *mid-2022.
Target date to open the new Valley View Ave. off ramp from southbound I-5 is *revised to end of July 2020 due to extensive rain delays. 
N. Firestone Blvd. reverts to two lanes in each direction east of Valley View Ave.: End of 2021. 
N. Firestone Blvd. re-opens between Knott Ave. and Trojan Way: *summer of 2020. 
New S. Firestone Blvd. running under the Valley View Ave. Bridge opened July 13, 2020. 
I-5 Valley View Ave. Interchange projected date of completion: Revised to *mid-2022.

Workers  completed installation of a rebar “mat” and stem walls on the deck of the second half of the north end of the bridge and are constructing falsework (temporary frame) and soffit (deck underside) on the south end. The contractor is also constructing support columns for the new Valley View Ave. on ramp to southbound I-5 and the S. Firestone Blvd. off ramp from the bridge and constructing a pedestrian crosswalk on the first half of the bridge. 

Videos & slide show from July 14 & July 28 below:

Photos from July 14  & July 28 below:

Reminder: The new S. Firestone Boulevard is now OPEN to through traffic in both directions all the way between Artesia Boulevard and Alondra Boulevard (via Marquardt Avenue) underneath the Valley View Avenue Bridge! Please note the on ramp to southbound I-5 from S. Firestone Boulevard remains CLOSED. Video & map below: 