VALLEY VIEW AVENUE INTERCHANGE PROJECT – Jan 21, 2018

Southbound I-5 Artesia Boulevard off-ramp will be closed tonight Friday, Jan. 19 from 8 p.m. to 6 a.m. Saturday, Jan. 20, to perform emergency repair work. Motorists will be directed to exit Carmenita Road and turn right, then turn left onto Artesia Boulevard. The ramp closure is shown on the map below in red; the detour route is shown in blue.

Crews will continue falsework installation on the second half of the slab bridge near Arbor Place and will start removing falsework from the first half of the slab bridge. In addition, crews will continue installing a drainage system on North Firestone Boulevard at Trojan Way, as well as continuing grading and work on the sewer system along South Firestone Boulevard.

The contractor is driving piles adjacent to southbound I-5 and Valley View bridge. This work will be conducted weekdays during the daytime between 7 a.m. and 3:30 p.m.

DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.

Print Friendly, PDF & Email