Valley View Ave. Interchange Project – December 6- December 13, 2019

Construction on this project is 50% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Opened to traffic Monday, October 7, 2019. Second southbound lane will open by early 2021. 
Completion of second half of Valley View Ave. Bridge: Revised to *late 2021.
Target date to open new Valley View Ave. off ramps from NB & SB I-5 and Valley View Ave. on ramp to NB I-5 is late February 2020. 
N. Firestone Blvd. reverts to two lanes in each direction east of Valley View Ave.: End of 2021. 
N. Firestone Blvd. re-opens between Knott Ave. and Trojan Way: by early 2020. 
I-5 Valley View Ave. Interchange projected date of completion: Revised to *end of 2021.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

The contractor is constructing the foundation for abutment wall and placing forms over the retaining walls for the Firestone Blvd. ramp where it will connect to the second half of the Valley View Ave. Bridge. Videos below from November 19 and November 26:

 

Photos below from November 19 through December 3:

 

The steel girders, rebar, and concrete from the demolished second half of the Valley View Ave. Bridge have been removed for recycling. Workers are now removing falsework (temporary frame support) from the completed first half of the bridge. Videos below show progress from Nov. 11 to Nov. 19:



Photos below from November 19 and November 26:

Workers are also excavating to install footings for the second half of the bridge and for the foundation of a “second” Firestone Blvd. that will run beneath the bridge between Marquardt Ave. and Artesia Blvd. Video below from November 26:

Photos below from November 26 and December 3:

Photos below show construction of abutment wall for Valley View Ave. on ramp where it will connect to southbound I-5 from Oct.22 through Nov. 19:

The contractor has poured the first layer of concrete called “lean concrete base” for a portion of the future Valley View Ave. on ramp to northbound I-5 east of the freeway in Santa Fe Springs. Photos below from December 3: