VALLEY VIEW AVENUE INTERCHANGE PROJECT – Aug 13, 2017

In the next week or two, crews will close the southbound Valley View Avenue left hand turn lane to S. Firestone Boulevard.  This will be a long term closure for approximately 18 months,  Motorists will be detoured to go south on Artesia Boulevard to access southbound I-5 freeway on-ramp (shown in red on the map below; detour route highlighted in green).

Pile driving and shoring activities are ongoing on the south side of Valley View Avenue. This work will be conducted weekdays during the daytime between 7 a.m. and 3:30 p.m.

 

DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.