ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT – Week of July 19, 2015

The new southbound I-5 Rosecrans on and off-ramps opened to the traffic last week. Next week, work on the Rosecrans Avenue bridge will require partial lane closures on Rosecrans Avenue under I-5. While the street will remain open to through-traffic, crews will close one lane in each direction on Rosecrans Avenue (between Bloomfield Avenue and Firestone Boulevard), daily between 9 a.m. and 3 p.m., Monday, July 20 through Friday, July 24.

 

On Thursday night, July 23, Rosecrans Avenue will be closed to traffic in both directions under I-5 (between Bloomfield Avenue and Firestone Boulevard), from 9 p.m. to 5 a.m. Friday, July 24. Motorists will be detoured along the routes highlighted in green on the map below.

Work area is highlighted in red; local access will be maintained for residents and businesses off Bloomfield Avenue and Firestone Boulevard.No access to Rosecrans Avenue underneath I-5 freeway. Rosecrans Avenue I-5 on and off-ramps will also be closed while this work is completed. Motorists will be directed to follow the detour routes highlighted in green, to bypass the closure area

Work area is highlighted in red; local access will be maintained for residents and businesses off Bloomfield Avenue and Firestone Boulevard.No access to Rosecrans Avenue underneath I-5 freeway. Rosecrans Avenue I-5 on and off-ramps will also be closed while this work is completed. Motorists will be directed to follow the detour routes highlighted in green, to bypass the closure area

Finally, a nighttime full closure of northbound I-5 at Rosecrans Avenue will be needed next week. The date and time for this closure has not been set, but more information will be provided as soon as the schedule for this work is finalized.