ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT – Week of February 14, 2016

Crews will be working during the daytime this week to place rebar to form the stem and soffits of the bridge as part of the widening. This work will take place weekdays (Monday through Friday) between 6:30 a.m. and 3 p.m. and will be ongoing for approximately two weeks.

In addition to this work, crews are preparing to open the new Silverbow Avenue pedestrian overcrossing in mid- to late- February.