ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT – Week of August 2, 2015

Daytime crusher activities in the center of the freeway will likely be completed next week; this work is ongoing in the median of the freeway, in order to process and recycle concrete and debris that was produced after the demolition of the Silverbow Avenue pedestrian bridge and the Rosecrans Avenue bridge.
Beginning Monday, Aug. 3 the contractor will commence pile driving activity in the center median of the freeway, to work on the new Bloomfield Avenue bridge. This work will take place Monday through Friday between 7 a.m. and 3:30 p.m. This work will be ongoing for approximately one week. The contractor anticipates pile driving activity will begin at the Rosecrans Avenue bridge in September.

Please be advised this work may be loud and disruptive due to equipment noise, vibration and pounding related to pile driving activity.