ROSECRANS Ave & BLOOMFIELD Ave Bridge Project – Week of Nov 12, 2017

Over the next few weeks crews may take intermittent daytime lane closures on Rosecrans Avenue at I-5, Mondays through Fridays between 8:30 a.m. and 3:30 p.m. At least one lane will remain open in each direction on Rosecrans Avenue at all times. These lane closures are needed to complete installation of overhead signs and to pour curb and gutter.

The week of Nov. 26 crews are tentatively planning nighttime full closures on northbound and southbound I-5 at Rosecrans Avenue, in order to restripe the freeway and shift k-rail. On Wednesday night, Nov. 29 crews will close northbound I-5 and on Thursday night, Nov. 30 and Friday night, Dec. 1 crews will close southbound I-5. Additional information regarding this work, including closure limits, times and recommended detour routes, will be provided as details are finalized.

 

 

 