Demolition activity of a portion of the Pioneer Boulevard has been completed. On Sunday, Aug. 23 crews will begin mobilizing equipment to conduct CIDH drilling at the Imperial Highway overcrossing. This work will be conducted from 8:30 p.m. Sunday, Aug. 23 to 6 a.m. Monday, Aug. 24.
Daytime partial lane closures (one lane in each direction) will be ongoing on San Antonio Drive at I-5, Imperial Highway at I-5, and Pioneer Boulevard at I-5, may be in effect, weekdays (Monday through Friday) between 9 a.m. and 3 p.m.
Work on Union Street, between San Antonio Drive and Paddison Avenue, is ongoing and will be underway for a few more weeks. Union Street is being widened, sidewalks will be reconstructed and the street will become a cul-de-sac adjacent to San Antonio Drive. Access for local residents will be maintained at all times. Construction activity is also ongoing with several sound walls along the northbound and southbound I-5. In addition, work continues on the frontage roads along the northbound I-5 (Adoree Street) and southbound I-5 (Southbound Frontage Road).