Work will occur during daytime hours unless otherwise noted. The schedule is weather-permitting and subject to change.
➤ Construction Activities
SR-134 to Magnolia Boulevard
Los Angeles River Bridge: Crews continue working in the I-5 median to widen the bridge.
Providencia Avenue: Crews are installing fence barriers on the pedestrian bridge and painting.
I-5 Median: Crews are constructing the median concrete barrier.
Magnolia Boulevard to Buena Vista Street
I-5 at Buena Vista Street: Crews are constructing freeway bridge approach and departure slabs.
I-5 at Empire Avenue: Crews are drilling to construct piles for the freeway bridge.
Northbound San Fernando Boulevard On-Ramp: Crews are constructing the on-ramp shoulder pavement.
➤ Closures & Detours
SR-134 to Magnolia Boulevard
Northbound and Southbound I-5 Lane Closures: Intermittent northbound and southbound lane closures between 10 p.m. and 6 a.m., at times reducing I-5 to one or two lanes in either direction.
Alameda Avenue, Sonora Avenue, Western Avenue and South Flower Street Lane Closures: Intermittent daytime and nighttime street, ramp and lane closures on Alameda Avenue, Sonora Avenue, Western Avenue and South Flower Street through late 2019. Detours are posted.
South Flower Street: Parking is not allowed during the daytime on South Flower Street at the Providencia Avenue Bridge where crews are painting.
Magnolia Boulevard to Buena Vista Street
Northbound and Southbound I-5 Lane Closures: Intermittent nighttime northbound and southbound I-5 lane closures, at times reducing I-5 to one or two lanes in either direction between Magnolia Boulevard and Hollywood Way from 9 p.m. to 6 a.m.
Buena Vista Street Closures: Intermittent daytime and nighttime closures of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue. A detour is posted.
On- and Off-Ramp Closures: Intermittent on- and off-ramp closures at Buena Vista Street, San Fernando Boulevard and Burbank Boulevard from 9 p.m. to 6 a.m. Detours are posted.