I-5 NORTH Construction Advisory – SR-134 to Buena Vista Street, June 12-19, 2020

Work will occur during daytime hours unless otherwise noted. The schedule is weather-permitting and subject to change.

Construction Activities

SR-134 (Ventura Freeway) to Magnolia Boulevard

I-5 between SR-134 and Magnolia Boulevard: Crews are installing joint seals, the irrigation system, landscaping and fencing. Some of this work occurs at night.

Verdugo Avenue at I-5: Crews are working on the abutment and the sidewalk under the I-5 bridge at Verdugo Avenue.

Magnolia Boulevard to Buena Vista Street

I-5 at Burbank Boulevard: Crews are excavating, constructing retaining walls and completing removal of the old Burbank Boulevard bridge. Some of this work occurs at night.

Pile Driving at Burbank Boulevard: Pile driving is underway to construct the foundation of the new I-5 Burbank Boulevard Bridge.

  • Pile driving occurs between 6:30 a.m. and 4 p.m. Monday through Friday. The schedule is subject to change.
  • No pile driving is scheduled on weekends. The schedule is subject to change.
  • Noise is expected during this operation.
  • Please see the Construction Notice below:

I-5 between Burbank Boulevard and Cohasset Street: Crews are constructing the drainage system in the median barrier.

Closures & Detours

SR-134 (Ventura Freeway) to Magnolia Boulevard

Intermittent Northbound and Southbound I-5 Lane Closures: Intermittent northbound and southbound lane closures between 10 p.m. and 6 a.m., at times reducing I-5 to one or two lanes in either direction.

Alameda Avenue, Sonora Avenue, Western Avenue and South Flower Street Lane Closures: Intermittent daytime and nighttime street, ramp and lane closures on Alameda Avenue, Sonora Avenue, Western Avenue and South Flower Street. Detours are posted.

Verdugo Avenue Closures: Intermittent lane closures may occur on Verdugo Avenue at the I-5 bridge. The shoulder may be closed during the day.

Magnolia Boulevard to Buena Vista Street

Long-term I-5 Ramp Closures at Burbank Boulevard: Long-term or permanent ramp closures are in effect at some of the I-5 on-and-off ramps at Burbank Boulevard. Detours are posted. Only the following ramps at Burbank Boulevard are OPEN:

  • The Northbound I-5 off-ramp to Eastbound Burbank Boulevard — Vehicles exiting I-5 must turn right and go east on Burbank Boulevard to San Fernando Boulevard. This ramp may be closed at times due to construction; a detour is provided.
  • The Southbound I-5 off-ramp to Westbound Burbank Boulevard — Vehicles exiting I-5 must turn right and go west on Burbank Boulevard to the intersection at Victory Boulevard. This ramp may be closed at times due to construction; a detour is provided.

Long-term Closure of Burbank Boulevard at I-5: At the I-5 bridge, Burbank Boulevard is closed to through traffic in both directions between San Fernando Boulevard and Front Street until approximately mid-2021. Detours are posted.

Northbound and Southbound I-5 Lane Closures: Intermittent northbound and southbound lane closures between 9 p.m. and 6 a.m., at times reducing I-5 to one or two lanes in either direction.

On- and Off-Ramp Closures and Lane Closures:  Intermittent on- and off-ramp closures and lane closures at Buena Vista Street, Empire Avenue,  San Fernando Boulevard and Burbank Boulevard from 9 p.m. to 6 a.m. Detours are posted.

 