I-5 NORTH Construction Advisory – SR-134 to Buena Vista Street, January 18-25, 2019

Work will occur during daytime hours unless otherwise noted.

Construction Activities

SR-134 to Magnolia Boulevard

Sonora Avenue, Alameda Avenue, Western Avenue, Providencia Avenue, and LA River Bridges: Crews are working in the I-5 median to widen the bridges.

Providencia Avenue: Crews are installing fence barriers on the pedestrian bridge and constructing the median concrete barrier. 

I-5 Median: Crews are installing drainage at night and during the day. Crews are placing concrete pavement at night and constructing the median concrete barrier at night.

Magnolia Boulevard to Buena Vista Street

Northbound I-5 between Burbank Boulevard and Cohasset Street: Crews are installing joint seals at the Burbank Western Channel cover, and paving.

Northbound and Southbound On-Ramps and Off-Ramps at Empire Avenue: Crews are paving the on- and off-ramps and constructing a water line at new Empire Avenue.

Closures & Detours

SR-134 to Magnolia Boulevard

Alameda Avenue, Sonora Avenue and Western Avenue Lane Closures: Intermittent daytime and nighttime street and lane closures on Alameda Avenue, Sonora Avenue and Western Avenue through late 2019. Detours are posted.

Northbound and Southbound I-5 Lane Closures: Intermittent northbound and southbound lane closures between 10 p.m. and 6 a.m., at times reducing I-5 to one or two lanes in either direction.

Magnolia Boulevard to Buena Vista Street

Northbound and Southbound I-5 Lane Closures: Intermittent nighttime northbound and southbound I-5 lane closures between Magnolia Boulevard and Hollywood Way from 9 p.m. to 6 a.m.

Buena Vista Street Closures: Intermittent daytime and nighttime closures of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue.

On- and Off-Ramp Closures: Intermittent on- and off-ramp closures at Buena Vista Street, San Fernando Boulevard and Burbank Boulevard from 9 p.m. to 6 a.m.  Detours will be provided. SPECIAL NOTICE, JAN. 20-21:  The Northbound I-5 off-ramp at Buena Vista Street is scheduled to close for paving from 7 p.m. Sunday, January 20, to 6 a.m. Monday, January 21, 2019. The Northbound I-5 on-ramp at Buena Vista Street is scheduled to close for paving from 8 p.m. Sunday, January 20, to 6 a.m. Monday, January 21, 2019. Detours are provided.  The schedule is weather-permitting and subject to change.

 

 