I-5 Construction Advisory – SR-134 to Buena Vista Street, Nov. 14-18, 2016

Happy Veterans Day! There will be no construction-related closures from Thursday, Nov. 10, at 6 a.m. to Sunday, Nov. 13, at midnight.

Full Northbound and Southbound I-5 Closures: The nights of November 14-18, northbound and southbound I-5 will be fully CLOSED in Burbank between Burbank Boulevard and Alameda Avenue. The closure window is midnight to 4 a.m.  More information and a detour map are here. Rain may cause closures to be cancelled and postponed until the following night.

Leland Way Sign Structure Installation:  This operation is postponed until late November/early December.

Construction activities and closures are subject to change.

Please remember, illegal dumping is a crime. Violators will be prosecuted.

➤ CONSTRUCTION ACTIVITIES for Nov. 14-18, 2016

Work will occur during daytime hours unless otherwise noted.

SR-134 to Magnolia Boulevard

Providencia Avenue Bridge: Girder erection (night work) and bridge construction work on the underside of the bridge both northbound and southbound sides. More information is here.

I-5: Install temporary shoring in median, northbound and southbound sides (night work).

LA River Bridge: Removal work (night work).

Magnolia Boulevard to Buena Vista Street

Empire I-5 Undercrossing: Backfill abutment walls, erect falsework and soffit.

Buena Vista Street Bridge (Winona Bridge): Install forms and rebar for center span’s stem and soffit (top portion of bridge).

Empire Avenue Railroad Underpass: Waterproof steel deck. Install forms and rebar, pour concrete, strip coping on retaining wall.

Empire Avenue:  Install forms and rebar, strip walls west of Victory Place. Install water mains on east side of I-5 (San Fernando Road).

Hollywood Way to Buena Vista Street:  Install cable railing, place railroad ballast, install signalization conduits and concrete ties.

Victory Place and Empire Avenue:  Grade street and intersection.

Northbound I-5 San Fernando Boulevard On-Ramp:  Remove retaining wall. Construct footing and walls.

Pump Building:  Structure backfill and form vault room floor.

➤ CLOSURES for Nov. 14-18, 2016

SR-134 to Magnolia Boulevard   

Closures will be implemented November 14-18 unless otherwise specified.

+ The nights of November 14-18, northbound and southbound I-5 will be fully CLOSED in Burbank between Burbank Boulevard and Alameda Avenue.  The closure window is midnight to 4 a.m.  Rain may cause closures to be cancelled and postponed until the following night.  More information and a detour map are here.

+ Intermittent lane closures on Flower Street between Alameda Avenue and Verdugo Avenue at night. Traffic flow will be maintained in both directions. Watch for flaggers. More information is here.

+ The southbound I-5 Alameda Avenue off-ramp will be closed from 9 p.m. to 6 a.m.

The southbound I-5 Burbank Boulevard on-ramp will be closed from 9 p.m. to 6 a.m.

The southbound I-5 Verdugo Avenue on-ramp will be closed from 9 p.m. to 6 a.m.

+ Westbound SR-134 will be closed at the LA River bridge from midnight to 5 a.m. A signed detour will be posted.

+ Through mid-2017 there will be intermittent daytime bike path closures between Riverside Drive and just south of the SR-134 overcrossing in the City of Los Angeles. When the path is closed, a signed detour will direct users to Zoo Drive and Western Heritage Way. See map here.

Magnolia Boulevard to Buena Vista Street 

+ Full closure of Empire Avenue between Wilson Avenue and Victory Place through late November 2016. Work hours will be from 6 a.m. to 4 p.m., primarily Monday through Friday. The closure will remain in place 24/7. A detour will be posted. Click here for more information.

Click HERE to see these closures on an interactive map.

 

 

 

 

 