I-5 Construction Advisory – SR-134 to Buena Vista Street, Apr 7-14, 2017

There will be a 55-hour closure of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue beginning April 21 at 9 p.m. through April 24 at 6 a.m to remove falsework from the Buena Vista Bridge.  Detours will be provided. 

Please remember, graffiti is a crime.  Violators will be prosecuted.

Construction Activities

Work will occur during daytime hours unless otherwise noted.

SR-134 to Magnolia Boulevard

Sonora, Western, Alameda Bridges: Crews are backfilling the median abutments for the Sonora, Western and Alameda Bridges.

Providencia Bridge:  Crews are working on the deck for the bridge.

Magnolia Boulevard to Buena Vista Street

Empire Avenue: Crews are removing the temporary shoring and excavating the retaining walls.  At southbound I-5 and Empire Avenue, crews are constructing the approach slab (the transition between roadway pavement and the bridge).

Hollywood Way to Burbank Boulevard (Railroad):  Crews are removing the shoofly (temporary tracks) and removing the railroad crossing at Buena Vista Street and installing fascia (decorative panels) on the side of the Buena Vista Bridge.

Northbound I-5 San Fernando Boulevard On-Ramp: Crews are constructing the walls and removing trees and other vegetation along San Fernando Boulevard.

Southbound I-5 at Buena Vista Street:  Crews are constructing approach slabs.

Closures & Detours

SR-134 to Magnolia Boulevard

Intermittent Daytime Closures on Flower Street.
Flower Street under the I-5 bridge will be closed intermittently during the day from 9 a.m. to 3 p.m.

Lane closures for Sonora Avenue, Western Avenue and Alameda Avenue.
Intermittent daytime lane closures, 9 a.m. to 3 p.m., under the I-5 bridge. Traffic will be maintained in both directions. Some sidewalk closures are expected as well. A pedestrian detour will be provided.

Northbound and Southbound I-5 Closures.
The number 3 and 4 lanes (far right lanes) will be intermittently closed from 11 p.m. to 5 a.m. on both northbound I-5 from Western Avenue to Alameda Avenue and on southbound I-5 from Verdugo Road to Alameda Avenue.

Magnolia Boulevard to Buena Vista Street

Buena Vista Street Closures.
Intermittent daytime and nighttime closures of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue.

There will be a 55-hour closure of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue beginning April 21 at 9 p.m. through April 24 at 6 a.m to remove falsework from the Buena Vista Bridge. Detours will be provided.

Northbound and Southbound I-5 Lane Closures.
Intermittent nighttime northbound and southbound I-5 lane closures between Magnolia Boulevard and Hollywood Way from 9 p.m. to 6 a.m.

On- and Off-Ramp Closures.
Intermittent on- and off-ramp closures at Buena Vista Street, San Fernando Boulevard and Burbank Boulevard from 9 p.m. to 6 a.m. Detours will be provided.

San Fernando Boulevard Closure.
Intermittent daytime closures on San Fernando Boulevard between Empire Avenue and the San Fernando on-ramp from 9 a.m to 3 p.m.  Flaggers will be onsite.

Empire Avenue Closure.
Full closure of Empire Avenue between Wilson Avenue and Victory Place through fall 2017. The closure will remain in place 24/7 and the pedestrian crossing will remain open. A detour will be posted.

 