I-5 Construction Advisory – Magnolia Blvd to Buena Vista Street, November 19-28, 2021

The following work will occur during daytime hours unless otherwise noted.  The schedule is weather-permitting and subject to change. For an overview of this project, please see: http://my5la.com/magnolia-boulevard-to-buena-vista-street/

Construction Activities

I-5 at Burbank Boulevard: Crews are doing electrical work; traffic signal work; installing traffic signs; installing lane striping; completing concrete barriers; installing traffic loop detectors in pavement; and testing signal systems and lighting. Crews are working in the I-5 median. Some work occurs at night.

I-5 between Empire Avenue and Cohasset Street: Crews are constructing the irrigation system.

Construction Completion: The new I-5 Burbank Boulevard Bridge opened for traffic on Burbank Boulevard shortly after 10 a.m. the morning of Wednesday, November 24. Drive across the new bridge with us in the video below: 

Closures & Detours

Recent closures on Burbank Boulevard, Front Street and I-5 Burbank Boulevard Ramps have been reopened. 

The following locations, which were closed recently, are now open for traffic:

  • Burbank Boulevard between San Fernando Boulevard and Victory Boulevard/Victory Place.
  • Front Street south of Burbank Boulevard.
  • The Northbound I-5 Burbank Boulevard off-ramp and on-ramp.
  • The Southbound I-5 Burbank Boulevard off-ramp and on-ramp.

Also, please be aware of the following closures:

Northbound and Southbound I-5 Lane Closures: Intermittent northbound and southbound lane closures may occur between 9 p.m. and 6 a.m., at times reducing I-5 to one or two lanes in either direction.

I-5 On-Ramp and Off-Ramp Closures: Some Northbound I-5 and Southbound I-5 on-ramps and off-ramps may be closed at times due to construction. Detours are provided.

Street Lane Closures: Intermittent street lane closures are possible on San Fernando Boulevard, Burbank Boulevard, Front Street, Buena Vista Street, Old Empire Avenue, Victory Place and other locations, either during the day or at night. Detours are provided.

The schedule is weather-permitting and subject to change.

 