Crews are constructing numerous elements of the I-5 HOV (Carpool Lanes) Widening and Interchange Improvements Project between Magnolia Blvd and Buena Vista Street in Burbank. The new lanes are scheduled to open this year. Work being done now includes grinding pavement, sealing joints, constructing the drainage, electrical and irrigation systems, and other work.  Here are some pictures of the progress during April and May 2022.

Below: Crews are planting landscaping along I-5. Reclaimed (recycled) water will be used to irrigate this new landscaping planted at the Northbound I-5 Burbank Blvd on-ramp.

Below: Crews planted this landscaping at the Northbound I-5 Burbank Blvd off-ramp.

Below: Crews are constructing concrete curbs and gutters, pedestrian ramps, and pavement on city streets at many locations in the I-5 construction zone. The location shown here is on Walnut Avenue adjacent to the new Northbound I-5 Burbank Blvd on-ramp.

Below: A foreman measures the inside of a new drainage inlet as crews construct the drainage system on I-5.

Below: Crews installed this additional traffic signal on Burbank Blvd at the intersection with the Northbound I-5 Burbank Blvd off-ramp as a traffic safety enhancement.

Below: Crews installed this new traffic signal at the southwest corner of the intersection of Victory Place and Old Empire Avenue, next to the new I-5 Empire Avenue interchange. In these photos, the traffic signal has not been activated so the signal heads are turned away from traffic.

Below: Another view of the new traffic signal system installed at Victory Place and Old Empire Avenue, showing the installation at the northeast corner of the intersection. At the right side of the photo are the elevated railroad tracks, a transportation safety enhancement which is part of this project and was completed earlier.

Below: Crews installed energy-efficient LED wall-mounted lighting on Empire Avenue under the I-5 bridge as a safety enhancement.

Below: Crews installed pendant (hanging) LED lighting fixtures on Empire Avenue under the railroad overpass as a safety enhancement.

Crews are continuing to work on the HOV (High Occupancy Vehicle, or carpool) lanes in both directions in the I-5 median between Magnolia Blvd and Buena Vista Street. The new lanes are scheduled to open this year. This view is facing south at Burbank Blvd. The red lines and arrow have been added to indicate the median area where the carpool lanes are being constructed.

 