FLORENCE AVENUE INTERCHANGE PROJECT – Week of Sept 17, 2017

On Thursday night, Sept. 14 crews will be performing potholing to locate underground utilities, within in the right hand turn pocket from Florence Avenue onto Orr and Day Road. In order to complete this work crews will close the far right hand turn lane from Florence Avenue onto Orr and Day Road from 9 p.m. Thursday, Sept. 14 to 6 a.m. Friday, Sept. 15. Crews anticipate being able to complete their work within approximately four to six hours. Please be advised, this work may cause intermittent noise disruption, but is not expected to generate sustained loud construction activity.

Sunday night, Sept. 17 through Tuesday night, Sept. 19 crews plan to remove falsework or temporary bridge supports, from the Florence Avenue bridge. This activity will require the full closure of northbound and southbound I-5 at Florence Avenue. This work is not expected to generate excessive noise.

The following closures are planned Sunday night, Sept. 17 through Tuesday night, Sept. 19, to allow crews to complete this work. The closure area is shown on the map below in red.

  • Northbound I-5 will be closed between Norwalk Boulevard and I-605 from 11:59 p.m. to 5 a.m., Sunday night, Sept. 17 through Tuesday, night, Sept. 19
    DETOUR: Motorists will exit northbound I-5 at Imperial Highway off-ramp, turn left on Imperial Highway, turn right on Firestone Boulevard and proceed to the northbound I-605 on-ramp; then transition onto northbound I-5. The detour route is shown on the map below in green.
  • Southbound I-5 will be closed between I-605 and Norwalk Boulevard, from 11 p.m. to 5 a.m., Sunday night, Sept. 17 through Tuesday night, Sept. 19
    DETOUR: Motorists will be directed onto SB I-605 to exit Firestone Boulevard, east on Firestone Boulevard, east on Imperial Highway, south on Southbound Frontage Road to access the southbound I-5 on-ramp. The detour route is shown on the map below in blue.

  • Northbound I-605 Connector to Southbound I-5 closed from 9 p.m. to 6 a.m., Sunday night, Sept. 17 through Tuesday night, Sept. 19
    DETOUR: Motorists will exit NB I-605 at Imperial Hwy. off-ramp, east on Imperial Hwy., south on Southbound Frontage Rd. to access SB I-5 on-ramp
  • Southbound I-605 Connector to Southbound I-5 closed from 9 p.m. to 6 a.m., Sunday night, Sept. 17 through Tuesday night, Sept. 19
    DETOUR: Motorists will continue on SB I-605, exit Firestone Blvd. off-ramp, east on Firestone Blvd., east on Imperial Hwy., south on Southbound Frontage Rd. to access SB I-5 on-ramp
  • Northbound I-5 Connector to Northbound I-605 closed from 9 p.m. to 6 a.m., Sunday night, Sept. 17 through Tuesday night, Sept. 19
    DETOUR:
    Motorists will exit northbound I-5 at Imperial Highway off-ramp, turn left on Imperial Highway, turn right on Firestone Boulevard and proceed to the northbound I-605 on-ramp.
  • Northbound I-5 Connector to Southbound I-605 closed from 9 p.m. to 6 a.m., Sunday night, Sept. 17 through Tuesday night, Sept. 19 DETOUR: Motorists will exit northbound I-5 at Imperial Highway off-ramp, turn left on Imperial Highway, proceed straight to access southbound I-605 on-ramp.

This information can also be found on the project Google map at the bottom of this page.

The week of Sept. 17 crews will pour concrete in the center median of I-5 at Florence Avenue. In order to complete this work, crews will close the two inside lanes on I-5 from Florence Avenue to I-605, nightly, Wednesday, Sept. 20 through Thursday, Sept. 21, between 9 p.m. and 6 a.m.

Crews have begun work to construct the new sound wall along the northbound I-5 Florence Avenue on-ramp, adjacent to Longworth Avenue. Crews hope to complete drilling CIDH (cast in drilled hole) piles along northbound I-5 this week. This operation will be conducted weekdays, between 6:30 a.m. and 3:30 p.m.

A portion of the sidewalk on Longworth Avenue, adjacent to the northbound I-5, has been closed to accommodate sound wall reconstruction. A chain link fence has been installed to close this area of the sidewalk from public access through the end of 2017. The sidewalk will be restored once sound wall construction is complete. While the sidewalk is being reconstructed, the sidewalk across the street from this work is open and accessible for public use.