FLORENCE AVENUE INTERCHANGE PROJECT – Week of October 9, 2016

Crews have resumed pile driving activity along northbound I-5 at Florence Avenue. Work will be conducted weekdays, between 7 a.m. and 3:30 p.m. and will be ongoing intermittently for the next four to six weeks.

Crews are continuing daytime work on the cul-de-sacs along Dollison Drive in the City of Downey and Buell Street in the City of Santa Fe Springs. Work is intermittent Monday through Friday, between 7 a.m. and 3:30 p.m. for approximately two weeks. 