Florence Avenue Interchange Project – Week of October 19- October 26, 2018

This project is 73% complete.
Projected date of completion for the Florence Ave. Bridge: Early 2020.
Project date for completion of project: Early 2020. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

The contractor shifted southbound traffic on I-5 south of the Florence Ave. Bridge to the new lanes in the median on the night of September 30.  Then northbound lanes were shifted to the median lanes on the night of October 11. Photos below show before and after the lane shifts:

 

Now we are building new freeway lanes on the right shoulders of both directions of I-5. Photos below from October 16:

 

Construction of the sound wall along the Florence Av. on ramp to northbound I-5 is complete. This provides the final noise barrier for the residents on Longworth Ave. Photos below.  (Tap / click on photos for slide show and details): :

 

Print Friendly, PDF & Email