Florence Avenue Interchange Project – November 15 – November 22 , 2019

This project is 84% complete.
Projected date of completion for the Florence Ave. Bridge and Project: Early *April 2020.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

On southbound I-5, all lanes are scheduled to be closed from I-605 to Imperial Highway from 11 p.m. Monday, Nov. 18 until 5 a.m. Tuesday, Nov. 19 to shift traffic onto the new lanes in the median, set K-rail, and re-stripe lanes. The northbound and southbound I-605 connectors to southbound I-5 will also scheduled to be closed. 

  • Southbound I-5 DETOUR: Southbound I-5 traffic will be directed onto southbound I-605, exit east on Imperial Highway, south on southbound Frontage Road to the southbound I-5 on-ramp.
  • Northbound I-605 connector to Southbound I-5 closed between 9 p.m. and 5 a.m. DETOUR: Motorists will exit northbound I-605 at Imperial Highway off-ramp, east on Imperial Highway, south on SB Frontage Road to access the southbound I-5 on-ramp.
     
  • Southbound I-605 Connector to Southbound I-5 closed between 9 p.m. and 5 a.m. DETOUR: Motorists will continue on southbound I-605, exit east on Imperial Highway to Northbound I-5 or south on SB Frontage Road to access southbound I-5 on-ramp.

Alternate route: Use southbound I-5 to southbound I-605 to eastbound State Route 91 (Artesia Freeway) back to I-5.

Go to https://twitter.com/CaltransDist7 and https://twitter.com/My5LA for updates.

Photo below shows current southbound traffic (red arrows) and new lanes in median (green arrows):

The contractor is constructing “falsework” (temporary frame support) for the second half of the Florence Ave. Bridge in the median of I-5, just north of the existing bridge. Video below from November 5 and November 11:

 

Photos below from November 5 and November 11:

 

We opened a new FOURTH freeway lane to traffic on northbound I-5 from Alondra Blvd. to the Orr & Day railroad overhead north of Imperial Highway. At that point, it narrows back down to three lanes. After completion of the Florence Ave. interchange, the northbound fourth lane will be extended closer to I-605. We also opened a fourth lane on southbound I-5 from north of Imperial Highway all the way to the Orange County line near Artesia Blvd. Map below:

 

The contractor completed pouring concrete for the new lanes in the median of I-5 north and south of the Florence Ave. Bridge. Video below from October 1 shows 360 degree pan:

Drone aerial photos from Oct. 11 below:

The Florence Ave. on ramp to northbound I-5, and the Florence Ave. off ramp from northbound I-5 will all remain closed until the second half of the Florence Ave. Bridge is complete. This is per request by the cities of Downey and Santa Fe Springs, to minimize traffic congestion until the three additional bridge lanes are provided to handle the increase in vehicles. Construction of the second half of the bridge is underway. 

 