FLORENCE AVENUE INTERCHANGE PROJECT – Week of June 25, 2017

Fence installation, vegetation removal and sound wall removal along the northbound I-5 Florence Avenue on-ramp, adjacent to Longworth Avenue, will continue next week. Once the sound wall removal operation is completed, crews will immediately begin work to construct the new sound wall. A privacy fence has been installed along Longworth Avenue, adjacent to northbound I-5 freeway. This work will be conducted weekdays, between 7 a.m. and 3:30 p.m. Please be advised, this work may be loud and disruptive due to concrete demolition and removal, equipment noise, sound wall construction activities and truck back-up alarms.

 