Florence Avenue Interchange Project – July 31, 2020 – August 7, 2020

This project is 92% complete.
Projected date of completion for the Florence Ave. Bridge and Project: *October 2020. Winter rains caused more delays. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

CANCELLED: The contractor completed work early! The scheduled overnight closures of all lanes on NB & SB I-5 from I-605 to Norwalk Blvd. from 11 p.m. to 5 a.m. the nights of Tuesday 8/4, Wednesday 8/5, and Thursday 8/6 are cancelled. Bridge falsework has been removed.

Map below:

Workers have been removing  the falsework (temporary frame) from the bottom of the bridge; and assembling forms for the new pedestrian walkway, median, and traffic barrier. 

Video below from July 28:

 

Photos below  from July 14 & July 28

The Florence Ave. on ramp to northbound I-5, and the Florence Ave. off ramp from northbound I-5 will all remain closed until the second half of the Florence Ave. Bridge is complete. This is per request by the cities of Downey and Santa Fe Springs, to minimize traffic congestion until the three additional bridge lanes are provided to handle the increase in vehicles. Construction of the second half of the bridge is underway. 

 

 