Florence Avenue Interchange Project – July 10, 2020 – July 17, 2020

This project is 90% complete.
Projected date of completion for the Florence Ave. Bridge and Project: *October 2020. Winter rains caused more delays. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Overnight closures are scheduled for all northbound and southbound lanes on Interstate 5 (Santa Ana Freeway) between Interstate 605 (San Gabriel River Freeway) and Norwalk Boulevard to remove falsework (temporary frame) from the Florence Ave. Bridge. Closures are subject to change and are scheduled as follows:

There are no street or freeway closures scheduled for this project July 10 through July 17.

Workers will continue to disassemble falsework, pave the remaining southbound lanes beneath the bridge, and begin constructing a pedestrian walkway and traffic barrier rail on the bridge.

June 18.

 

Drone aerial video below shows new freeway lanes, new on and off ramps, and final concrete poured on second half of bridge:

P

Photo below from June 18:

Video below from June 9:

Photos below from June 9 and June 18:

Video slideshow below from May 1 & May 6:

Video below from May 6:

 

The Florence Ave. on ramp to northbound I-5, and the Florence Ave. off ramp from northbound I-5 will all remain closed until the second half of the Florence Ave. Bridge is complete. This is per request by the cities of Downey and Santa Fe Springs, to minimize traffic congestion until the three additional bridge lanes are provided to handle the increase in vehicles. Construction of the second half of the bridge is underway. 

 

 