FLORENCE AVENUE INTERCHANGE PROJECT – Week of January 29, 2017

Drainage system installation and construction along Longworth Avenue between Harvest Avenue and Orr and Day Road (adjacent to northbound I-5), is scheduled to begin Monday, Jan. 30, weather permitting. Work will be conducted weekdays between 6:30 a.m. and 3:30 p.m. and is expected to take one to two weeks to complete.

Crews will be performing signal work at Florence Avenue and Orr and Day Road, intermittently over the next two weeks, weekdays between 9 a.m. and 3 p.m. This work will require lane reductions on Florence Avenue at Orr and Day Road; please expect delays and use an alternate route if possible.

This weekend crews will be performing drainage work underneath the northbound I-605 connector to southbound I-5 freeway and will be repaving a trench on the connector. This work will require the connector to be closed from 7 p.m. Friday, Jan. 27 through 6 a.m. Monday, Jan. 30, weather permitting.

DETOUR ROUTE: Motorists will be directed to exit northbound I-605 at Imperial Highway, travel east on Imperial Highway, then south on SB Frontage Road to access the southbound I-5 freeway on-ramp. The northbound I-605 / southbound I-5 connector is shown in red on the map below and the detour route is shown in blue.

 

Additional information will be available on the Google project map below and on this website.

Pile driving operations have tentatively stopped along northbound I-5 at Florence Avenue and will resume in early 2017.