This project is 86% complete.
Projected date of completion for the Florence Ave. Bridge and Project: Late *June 2020. Winter rains have caused more delays. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Please note the scheduled overnight closure of all northbound and southbound lanes on Interstate 5 (Santa Ana Freeway) between Interstate 605 (San Gabriel River Freeway) and Norwalk Boulevard to realign the southbound I-605 connector to southbound I-5; install K-rail; stripe lanes; and adjust bridge falsework. Closures are subject to change and are scheduled as follows:

Tuesday, Jan. 21: from 12:01 a.m. until 5 a.m.
The
nights of Tuesday, Jan. 21, Wednesday, Jan. 22, & the night of Thursday, Jan. 23: 11 p.m. until 5 a.m.

  • Northbound and southbound I-5 closed between I-605 and Norwalk Boulevard. 
  • Northbound and southbound I-605 connectors to southbound I-5 closed. (Starting at 10 p.m.)

Alternate route: Use southbound I-5 to southbound I-710 (Long Beach Freeway) or to southbound I-605 to eastbound State Route 91 (Artesia Freeway) back to I-5. Or reverse route for northbound route.

Southbound detour: southbound I-5 to southbound I-605. Exit Imperial Highway eastbound to I-5, turn right on frontage road to soutbound on ramp.

Northbound detour: northbound traffic taken off at Norwalk Blvd. Either continue straight to Imperial Highway or turn right on Norwalk Blvd. to Imperial Highway. Then turn left on Imperial Highway to northbound I-605 to northbound I-5.

Go to https://twitter.com/CaltransDist7 and https://twitter.com/My5LA for updates.

These closures are scheduled for separate nights and will re-open each morning. Confirm closures at http://quickmap.dot.ca.gov/ .            

Map below:

The contractor installed a rebar “mat” across the soffit (underside) and outer “stem walls” of the deck of the second half of the new Florence Ave. Bridge over I-5 and constructed rebar frames for stem walls across the center of the deck. Workers have been encasing the stem wall frames in lumber forms in preparation for the first concrete pour. Video below from Dec. 10 and January 14 of 2020: 

Photos below from November 11, 2019 through January 14, 2020:

Workers have also constructed the soffit and outer stem walls of the second half of the bridge west of I-5. Video below from December 31, 2019:

Photos below from December 31, 2019:

Crews are now excavating  the closed lanes on the west side of I-5 to lower them up to four feet as they run beneath the new bridge and then re-paving. Photos below from December 3, 2019 through January 7, 2020:

The Florence Ave. on ramp to northbound I-5, and the Florence Ave. off ramp from northbound I-5 will all remain closed until the second half of the Florence Ave. Bridge is complete. This is per request by the cities of Downey and Santa Fe Springs, to minimize traffic congestion until the three additional bridge lanes are provided to handle the increase in vehicles. Construction of the second half of the bridge is underway. 

 

 