FLORENCE AVENUE INTERCHANGE PROJECT – Week of December 27, 2015

HOLIDAY UPDATE: In observance of the Christmas holiday, there are no closures scheduled Thursday, Dec. 24 through Sunday, Dec. 27 and Thursday, Dec. 31 through Sunday, Jan. 3.

Happy Holidays to you and your family on behalf of the I-5 South Corridor Improvements team!

Crews are working to form soundwalls along northbound and southbound I-5. Roadway excavation is underway behind k-rail and the construction fencing, along Mondon Avenue between Cecilia Street and Buell Street.

Shoring activity is still underway along the Orr and Day railroad bridge, which passes underneath the I-5 freeway. This work will take place weekdays (Monday through Friday) between 6:30 a.m. and 3 p.m. and will be ongoing for approximately the next three to four weeks.

 

 

 

 

 