Florence Avenue Interchange Project – Week of August 17 – August 24, 2018

This project is 68% complete.
Projected date of completion for the Florence Ave. Bridge: December of 2019.
Project date for completion of project: Late 2019. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Update: The tentatively scheduled overnight closure of I-5 for the night of Thursday, August 23 has been postponed until next week.

Longworth Ave. residents north of Florence Ave: You can look up from Longworth Ave. now and see construction of the sound wall along the Florence Av. on ramp to northbound I-5. Photos below from August 7 and August 14 show progress.  (Tap / click on photos for slide show and details): :

 

Final paving of the new freeway lanes for I-5 continues in the median south of the Florence Ave. Bridge. Once the lanes are paved, there will be a shift in traffic lanes utilizing the new lanes in the median. Photos below from August 7 and August 14 (facing north):

 

Florence Ave.: As of August 3, Florence Ave. is now two lanes in each direction over I-5; there are two left-turn lanes on westbound Florence Ave. at Studebaker Rd.; and there is a left-turn lane on eastbound Florence Ave. at Giant RV. Photos below from August 7:

 

 

 

 

 

 

 