Florence Ave Interchange Project – Week of April 26, 2015

Work is complete on the traffic signal at Roseton Avenue and Florence Avenue. The frontage road at Roseton Ave opened this week, and will allow through traffic onto Florence Avenue, during the upcoming closure of Orr and Day Road.

The Year-long closure of Orr and Day Road (from just south of the Florence Avenue to just north of Cecilia St) and Mondon Avenue between Lakeland Road and Ringwood Avenue) is tentatively scheduled to begin on Thursday, April 30. Click here for more  information.

During the week of April 26, crews will permanently close Dollison Drive (between QUinn Street and Southbound I-5 on-ramp) and southbound I-5 freeway on-ramp on Dollison Drive. Finally, a long-term (approximately three year) closure of the southbound I-5 on-ramp on Florence Avenue is schedule to begin the week of April 26. Click here for more information.

Print Friendly, PDF & Email