News-Rosecrans and Bloomfield Bridge Project
-
-
-
-
-
Rosecrans Ave. & Bloomfield Ave. Bridge Project – Week of Mar. 30 – Apr. 6, 2018
Construction on this project is 97% complete. The work that remains will include, landscaping, electrical work, striping and other finishing work. The contractor has completed installation of the pedestrian walkways along S. Firestone Blvd and along Shoemaker Ave. at the Shoemaker Ave. Overcrossing (below): The concrete decor […]
-
ROSECRANS Ave & BLOOMFIELD Ave Bridge Project – Week of Jan 21, 2018
On Monday, Jan. 8 crews opened the newly reconstructed northbound I-5 on- and off-ramp at Rosecrans Avenue and on Wednesday, Jan. 10 crews opened the Bloomfield Avenue undercrossing, allowing traffic to pass underneath the I-5 freeway. These major milestones mark a significant step toward completion of the Rosecrans Avenue & Bloomfield Avenue bridge project. All […]
-
ROSECRANS Ave & BLOOMFIELD Ave Bridge Project – Week of Jan 14, 2018
On Monday, Jan. 8 crews opened the newly reconstructed northbound I-5 on- and off-ramp at Rosecrans Avenue and on Wednesday, Jan. 10 crews opened the Bloomfield Avenue undercrossing, allowing traffic to pass underneath the I-5 freeway. These major milestones mark a significant step toward completion of the Rosecrans Avenue & Bloomfield Avenue bridge project. All […]
-
ROSECRANS Ave & BLOOMFIELD Ave Bridge Project – Week of Jan 7, 2018
This weekend there will be an extended 55-hour closure of Rosecrans Avenue at I-5. This closure is needed in order to reconstruct this section of the roadway to its final configuration and prepare to open the northbound I-5 on- and off-ramp at Rosecrans Avenue. On Friday, Jan. 5 from 9 a.m. to 8 p.m., crews […]
-
ROSECRANS Ave & BLOOMFIELD Ave Bridge Project – Week of Dec 31, 2017
Over the next few weeks crews may take intermittent daytime lane closures on Rosecrans Avenue at I-5, Mondays through Fridays between 8:30 a.m. and 3:30 p.m. At least one lane will remain open in each direction on Rosecrans Avenue at all times. These lane closures are needed to complete installation of overhead signs and to […]
-
ROSECRANS Ave & BLOOMFIELD Ave Bridge Project – Week of Dec 24, 2017
Over the next few weeks crews may take intermittent daytime lane closures on Rosecrans Avenue at I-5, Mondays through Fridays between 8:30 a.m. and 3:30 p.m. At least one lane will remain open in each direction on Rosecrans Avenue at all times. These lane closures are needed to complete installation of overhead signs and to […]
-
ROSECRANS Ave & BLOOMFIELD Ave Bridge Project – Week of Dec 17, 2017
Over the next few weeks crews may take intermittent daytime lane closures on Rosecrans Avenue at I-5, Mondays through Fridays between 8:30 a.m. and 3:30 p.m. At least one lane will remain open in each direction on Rosecrans Avenue at all times. These lane closures are needed to complete installation of overhead signs and to […]
-
ROSECRANS Ave & BLOOMFIELD Ave Bridge Project – Week of Dec 10, 2017
Over the next few weeks crews may take intermittent daytime lane closures on Rosecrans Avenue at I-5, Mondays through Fridays between 8:30 a.m. and 3:30 p.m. At least one lane will remain open in each direction on Rosecrans Avenue at all times. These lane closures are needed to complete installation of overhead signs and to […]