CARMENITA ROAD INTERCHANGE PROJECT – January 8, 2017

This week, crews will close one lane on northbound Carmenita Road Bridge over I-5. The lane reduction will take place Monday, January 9 through Friday, January 13 between 9 p.m. and 5 a.m. The lane reduction is needed as crews install signage.

Electrical work along the shoulders of the northbound and southbound I-5 freeway at Carmenita Road is ongoing. This work will take place Monday through Friday between 7 a.m. and 4 p.m.

In addition to this work, landscape and irrigation work is ongoing along Frontage Road, N. Firestone Boulevard and S. Firestone Boulevard. This work will take place Monday through Friday between 7 a.m. and 4 p.m.

For full closure and detour information, please see the Google map below.

 