Burbank Blvd. Bridge Project – Gallery – January 2021

Southbound I-5 Traffic Switch at Burbank Blvd., Jan. 2021

Crews relocated traffic lanes onto newly constructed pavement on Southbound I-5 during a 55-hour-long operation from Friday, January 8, at 10 p.m. to Monday, January 11, at 5 a.m.

Southbound I-5 temporarily was reduced to only one or two lanes open for traffic between Empire Avenue and Magnolia Boulevard. Concrete barriers (or “K-rail”) were placed to provide a safe work zone for crews as they constructed final sections of pavement to complete the shift of traffic lanes.

 

 

 

 

 

 

 

 